District 29
HAMILTON COUNTY The tunnel cleaning of the McCallie Tunnel on US-11(US-64, SR-2), the Stringers Ridge Tunnel on US-127(SR-8), and the Bachman Tubes on US-41 (US-76, S.R.8): On Thursday April 22nd, from 8 PM-6 AM, the contractor will be closing down the Bachman Tunnels in East Ridge to clean the tunnels. There will be a signed detour for the traveling public to use.
[Diamond Specialized, Inc./Curtis/CNU182]
HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): During this reporting period, the contractor will be performing utility relocation work throughout the project limits, installing new drainage structures, and performing initial grading work for retaining wall construction. A traffic shift on I-24 eastbound has been implemented near MM 178 to allow for new construction on the right shoulder of the interstate. Brief intermittent lane closures are possible during daylight hours on SR-2 (Broad St.) and SR-58 (Market St.) to allow for moving equipment and utility relocation.
[Wright Brothers Construction Company, Inc./Wagner/CNU011]
HAMILTON COUNTY I-24 Replacement of Belvoir Ave. bridge over I-24 and I-24 bridges over Germantown Road near MM 183:Single and double alternating lane closures on I-24 EB and WB will be used on 04/22/21 and between 04/26/21 and 04/28/21 from 9 PM and 6 AM. There will be single lane closures in the north and south directions of Germantown Road under the I-24 Bridge and at the intersections of Germantown with North and South Terrace on 04/22/21 and between 04/26/21 and 04/28/21 from 9 PM and 6 AM.
[Bell and Associates Construction, LP/Blevins/CMGC03]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: Phase 2 traffic alignments have been implemented. Watch for trucks entering and exiting project. Traffic should expect multiple lane shifts traveling through the interchange. Lane closures will occur Sunday nights through Thursday nights between 9 PM and 6 AM at the following locations: I-75 NB MM 1, I-75 SB MM 3 and I-24 EB MM 184.0 Traffic pacing may occur throughout interchange Sunday nights through Thursday nights between 9 PM and 6 AM. Additionally, there may intermittent shoulder closures at various locations for access to the median and roadside areas. I-75 NB to I-24 WB split has been moved back 1500 feet from its previous location. Welcome Center traffic intending to use I-24 WB now, will have to detour on I-75 NB to Exit 3. Detailed detour information will be available at the Welcome Center. The speed limit has been reduced to 45 MPH throughout the interchange.
[C.W. Matthews Contracting Company, Inc./Blevins/DB1801]
HAMILTON COUNTY US-27 (I-124) widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: Weather Permitting, the contractor will implement a lane/shoulder closures daily between the hours of 7 PM and 6 AM. Note: Monday thru Friday from 6 AM to 7 PM a minimum of two lanes will remain open both Northbound and Southbound on U-S27. Monday thru Friday from 7 PM to 6 AM and Saturday and Sunday from 6 AM to 7 PM a minimum of one lane will remain open both Northbound and Southbound on US-27. Thursday 04/22/21 thru Wednesday 04/28/21 – 7 AM to 6 PM Temporary lane/shoulder closures will be in place for southbound and northbound US-27 from the Olgiati Bridge to I-24 for punch list items and clearance gauge markings. State Trooper Requests: Yes, State Troopers are requested for mainline and shoulder closures on Thursday, 04/22/21 thru Friday 04/23/21 and Monday, 04/26/21 thru Wednesday 04/28/21.
[Dement Construction Company, LLC/Curtis/CNP230]
HAMILTON COUNTY I-75 TDOT Maintenance both directions from MM 9.5 to MM 11.5: Lane closures in both directions of I-75 between MM 9.5 and MM 11.5 for bridge deck inspection. Closures will be on April 20th from 9 PM to 2 AM [TDOT/Wallace/MAINT]
HAMILTON COUNTY SR-319 (HIXSON PK.) Utility Work northbound from LM 8.14 to LM 8.11: Shoulder and single lane closure between Big Ridge Road and Gold Crest Drive. Arrow board, signage and cones will be present. Motorists should use caution through the area and be aware of personnel and equipment between 9 AM and 2 PM starting 04/13/21 through 04/30/21. [2021-091]
HAMILTON COUNTY SR-29 (US-27) repair of the bridge over Big Soddy Creek (LM 20.6): The contractor will be performing bridge & roadway repair on the SR-29 bridge over Big Soddy Creek. Southbound will be open completely with no lane restrictions. Northbound will have two lanes open and one lane closed. There is the potential for temporary closures at times.
[Mid-State Construction Company, Inc./Osbonlighter/CNU046]
HAMILTON COUNTY SR-2 (US-64, US-11) improvement of the intersection at Edgmon Road in Collegedale (LM 22.7), including grading, drainage, and paving: Extra care should be taken while trucks are entering and exiting the roadway. One lane might be intermittently closed while work is ongoing. Additional flaggers will be onsite as needed.
[Talley Construction Company, Inc./Osbonlighter/CNU012]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, to install power poles and transfer lines. The flagging operations will be performed on 04/22/21, 04/23/21, 04/26/21, 04/27/21, and 04/28/21 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be grading, paving, constructing retaining wall(s) and installing signals & lighting on S.I.A. route connecting Ferdinand Piech Way & Volkswagen Dr. The roadway is not open to traffic. The traveling public should be alert to the entrance and exit of construction vehicles from the jobsite onto the connecting roadways. Flaggers may be onsite directing traffic.
[Talley Construction Company, Inc./Osbonlighter/CNU221]