HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): On Sunday(2/27/22) through Friday(3/4/22) from 7 PM-7 AM, there will be 1 lane closed in either direction on Market St. as the contractor works on the new installation of the storm drainage on Market St. Williams Street is closed to all traffic at the I-24 underpass to support the installation of new storm drainage structures for the new frontage road. Traffic will still be able to access the ramps to I-24 and US-27, but no through traffic will be allowed on Williams Street between West 21st Street and West 25th Street. Traffic will detour around the closure via West 21st Street and Broad Street. Signs will be posted. The contractor will be working on new bridge construction, storm drainage structures, and utility relocation. Chestnut Street is closed at the I-24 underpass and will remain closed until the construction of bridge #2 is complete. Detour routes are posted. |
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: All roadways and ramps are in their final alignments. The contractor is now working on final items and traffic should still use caution traveling throughout the interchange. The final work items will mostly consist of off shoulder work/median work. Lane closures are planned for Sunday nights through Thursday nights between 9:00 PM and 6:00 AM to finish in roadway work. The speed limit will remain reduced to 45 MPH throughout the interchange until construction crews demobilize. |
HAMILTON COUNTY SR-153 (STATE HWY. 153) Utility Work northbound at LM 11.26: Shoulder and single lane closures between Grubb Road and Grubb Road with the work area across from Academy Sports/Kohls. Motorists should reduce speed and be prepared to stop. Signage, cones, and flaggers will be present, 03/01/22 from 9 am – 3 pm. [2022-113] |
HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work eastbound from LM 14.62 to LM 14.64: Shoulder and single lane closures on Brainerd Road between Eastgate Loop at Applebee’s to Eastgate Loop at Starbucks. Motorists should use the entrance at Applebee’s to access Eastgate Loop to avoid construction. Motorists should reduce speed and be prepared to stop. Signage, cones, and flaggers will be present, 02/28/22 through 03/11/22 from 9 am – 2 pm. [2022-096] |
HAMILTON COUNTY SR-58 (ALTON PARK BLVD.) Utility Work both directions at LM 3.09: Shoulder and single lane closures between W 33rd Street and W 37th Street. Motorists should reduce speed and be prepared to stop. Signage, cones, and flaggers will be present, 01/10/22 through 03/09/22 from 9 am – 2 pm. [2021-794, 2021-869, 2021-902] |
HAMILTON COUNTY SR-8 (RINGGOLD RD.) TDOT Maintenance northbound from LM 4.9 to LM 5.2: The north bound tunnel (East Ridge to Chattanooga) will be closed for maintenance on 02/24/2022 from 10 PM to 02/23/2022 at 5 AM. A detour will be in place. |
HAMILTON COUNTY SR-8 (RINGGOLD RD.) Utility Work westbound at LM 1.25: Shoulder closures between Mack Smith Road and McDonald Road. Motorists should reduce speed and be aware of personnel. Signage, cones, and flaggers will be present, 02/24/22 through 03/02/22 from 9 am – 2 pm. [2021-636] |
HAMILTON COUNTY SR-8 (TAFT HWY.) Utility Work both directions from LM 22.01 to LM 22.2: Shoulder and single lane closures between Fairmount Road and Dowler Lane. Motorists should reduce speed and be prepared to stop. Signage, cones, and flaggers will be present, 02/15/22 through 03/15/22 from 9 am – 2 pm. [2021-636] |
HAMILTON COUNTY SR-2 concrete repair using hot applied fiber reinforced polymer patching material from west of Cowart Street (LM 7.4) to Rossville Boulevard (LM 8.5): Starting Monday February 28th of this reporting period, the contractor will have 1 lane closed in either direction on SR2. |
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, to install power poles and transfer lines. The flagging operations will be performed on 02/24/22, 02/25/22, 02/28/22, 03/01/22, and 03/02/22 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment. A portion of Tucker Road has been closed from Spalding Drive to 5400 Tucker Road to allow for grading and utility operations. |
HAMILTON COUNTY SR-319 (Amnicola Highway) bridge repair over SR-153: Contractor will be performing bridge repair operations on the Amnicola (SR-319) bridge over SR-153. During this project, SR-319 will have lane closures in place. Bridge repair over 153 will be performed between 8pm & 6am. During repair operations at least one lane of traffic shall remain open in both directions. SR-153 at times will be down 2 lanes with motorist using the gore area during nighttime closures. Motorists are advised to use caution in this vicinity and remain aware of construction activities. |
HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be performing a grading operation at the roundabout connecting to S.I.A. route connecting Ferdinand Piech Way & Volkswagen Dr. During this report period, the roundabout will have one lane closed along with connecting roadways; one lane shall remain open at all times. Traveling public should be cautious of the new traffic pattern in effect including a lowered speed limit. The traveling public should also be alert to the entrance and exit of construction vehicles & staff from the jobsite onto the connecting roadways. Flaggers may be onsite directing traffic. |