HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): During this reporting period, the contractor will be working on the placement of earth fill and the construction of bridges. Chestnut street is closed to through traffic between West 20th Street and West 25th Street and will remain closed until the construction of bridge #2 is complete. The contractor may have brief intermittent lane closures on Broad Street (SR-2) and Market Street (SR-58) to support utility relocation Monday through Friday 8 AM to 5:30 PM.
[Wright Brothers Construction Company, Inc./Wagner/CNU011]
HAMILTON COUNTY I-24 Replacement of Belvoir Ave. bridge over I-24 and I-24 bridges over Germantown Road near MM 183: Single lane closures on North and South Terraces and in the north and south directions of Germantown Road under the I-24 Bridge and at the intersections of Germantown with North and South Terrace on 08/19/21, 08/20/21, and between 08/23/21 and 08/25/21 from 9 AM to 6 AM the following morning. There is a 45 MPH speed limit reduction throughout the project corridor on I-24.
[Bell and Associates Construction, LP/Blevins/CMGC03]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: The contractor is now working on final items and all roadway and ramps are in their final alignments. Traffic should still use caution travelling throughout the interchange. The final work items will mostly consist off the shoulder or in the median areas. Additionally, lane closures may still occur Sunday nights through Thursday nights between 9 PM and 6 AM to finish bridge grinding and concrete joint sealing. The speed limit will remain reduced to 45 MPH throughout the interchange until construction crews demobilize.
[C.W. Matthews Contracting Company, Inc./Blevins/DB1801]
HAMILTON COUNTY I-75 TDOT Contractor both directions from MM 0.70 to MM 2.70: During this report period, contractors will have temporary nighttime shoulder closures from 8 PM to 6 AM to perform survey work. [Wiser Consultants & Superior Traffic Control / Ford]
HAMILTON COUNTY SR-153 (STATE HWY. 153) Utility Work both directions from LM 8.58 to LM 7.15: Nighttime utility work will reduce both northbound and southbound lanes between the Chickamauga Dam and the North Gate Mall entrance to a single lane. Motorists should reduce speed and be aware of message boards, signage, and law enforcement through the area during the hours of 10 PM to 6 AM from 08/24/21 through 08/27/21. [2021-374]
HAMILTON COUNTY SR-17 (ST. ELMO AVE.) Utility Work both directions at LM 0.31: Lane closures at the intersection of St. Elmo Avenue and W 55th Street for utility construction. Motorists should use caution and be aware of personnel and equipment when traveling through the work zone. Signage, cones, and flaggers will be present between 9 AM and 2 PM with an estimated completion of 09/02/21. [2021-474]
HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work westbound at LM 13.84: Brainerd Road will have two westbound lanes closed for utility work between North Moore Rd and North St. Marks Avenue. Signage and barrels will be present. Motorists should expect delays and seek an alternate route between 8 AM and 5 PM from 08/03/21 – 08/25/21. [2021-502]
HAMILTON COUNTY SR-2 (E. 23RD ST.) Utility Work both directions at LM 9.82: Shoulder and single lane closures between 4th Avenue and S Lyerly Street. Signage and cones will be present. Motorists should use caution and be aware of personnel and equipment between 9 AM and 2 PM through 08/25/21. [2021-389]
HAMILTON COUNTY SR-29 (US-27) repair of the bridge over Big Soddy Creek (LM 20.6): The contractor will be performing bridge & roadway repair on the SR-29 bridge over Big Soddy Creek. During this report period the contractor will have temporary road closures. At least one lane of traffic in both directions will always remain open.
[Mid-State Construction Company, Inc./Osbonlighter/CNU046]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, to install power poles and transfer lines. The flagging operations will be performed on 08/19/21, 08/20/21, 08/23/21, 08/24/21, and 08/25/21 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. There will also be very short lane closures for blasting that will last five minutes or less. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY SR-319 (Amnicola Highway) bridge repair over SR-153: The contractor will be performing bridge repair operations on the Amnicola (SR-319) bridge over SR-153. During this project, SR-319 will have lane closures in place & SR-153 may have lane closures as well. Bridge repair over SR-153 will be performed between 8 PM & 6 AM. During repair operations at least one lane of traffic shall remain open in all directions.
[Mid-State Construction Company, Inc./Osbonlighter/CNV053]
HAMILTON COUNTY SR-321 resurfacing from north of SR-317 (LM 5.6) to near US-11 (US-64 / SR-2 / LM 7.1): During this report period, the contractor will have temporary lane closures while performing resurfacing operations. One lane of traffic will always remain open. Flaggers will be present to maintain traffic flow.
[Talley Construction Company, Inc./Osbonlighter/CNV054]
HAMILTON COUNTY SR-8 (US-41, US-76) Bachman Tubes cleaning: On Thursday night of this reporting period, the contractor will be closing the tunnels from 8 PM – 6 AM for cleaning. There will be a signed detour to reroute traffic around the closure.
[Diamond Specialized, Inc./Curtis/CNV157]
HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be grading, paving, constructing retaining wall(s) and installing signals & lighting on the S.I.A. route connecting Ferdinand Piech Way & Volkswagen Dr. **The roadway is not open to traffic**. The motoring public should be alert to the entrance and exit of construction vehicles from the jobsite onto the connecting roadways. Flaggers may be onsite directing traffic.
[Talley Construction Company, Inc./Osbonlighter/CNU221]