HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): During this reporting period, the contractor will be implementing a temporary closure of the I-24 Westramp to Northbound Broad Street (SR-2) to place temporary concrete barrier rail. This closure will begin at 9:00 PM on Friday 08/06/2021 and be complete by 6:00 AM Saturday 08/07/2021. Traffic accessing Broad Street from I-24 Westbound will be detoured to US-27 North Exit 1A (Carter Street/Main Street) and 13th Street. Signs will be posted for the detour route. Chestnut Street is closed to through traffic between West 20th Street and West 25th Street and will remain closed until the construction of bridge #2 is complete. The contractor may have brief intermittent lane closures on Broad Street (SR-2) and Market Street (SR-58) to support utility relocation Monday through Friday 8:00 AM to 5:30 PM.
[Wright Brothers Construction Company, Inc./Wagner/CNU011]
HAMILTON COUNTY I-24 Replacement of Belvoir Ave. bridge over I-24 and I-24 bridges over Germantown Road near MM 183: Single and double alternating lane closures on I-24 EB and WB will be used on 08/05/21 and 08/08/21 through 08/11/21 from 9:00 PM and 6:00 AM. Additionally, there will be single lane closures on North and South Terraces and in the north and south directions of Germantown Road under the I-24 Bridge and at the intersections of Germantown with North and South Terrace on 08/05/21, 08/06/21, and between 08/09/21 and 08/11/21 from 9:00 AM to 6:00 AM the following morning. There is a 45 MPH speed limit reduction throughout the project corridor on I-24.
[Bell and Associates Construction, LP/Blevins/CMGC03]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: Phase 4 traffic alignments have been implemented. Watch for trucks entering and exiting project. Traffic should expect multiple lane shifts traveling through the interchange. Lane closures will occur Sunday nights through Thursday nights between 9:00 PM and 6:00 AM at the following locations: I-75 NB MM 1, I-75 SB MM 3 and I-24 EB MM 184.0 Traffic pacing may occur throughout interchange Sunday nights through Thursday nights between 9:00 PM and 6:00 AM. Additionally, there may be intermittent shoulder closures at various locations for access to the median and roadside areas. The Welcome Center has been reopened. The speed limit has been reduced to 45 MPH throughout the interchange. The contractor will be performing paving and finishing activities on the interstate-to-interstate ramps beginning 08/06/2021 at 9:00 PM to 08/09/2021 at 6:00 AM. This work will require lane closures on the ramps throughout the weekend. Work will begin on the I-75 NB to I-24 WB ramp and then move to the I-24 EB ramps.
[C.W. Matthews Contracting Company, Inc./Blevins/DB1801]
HAMILTON COUNTY SR-17 (ST. ELMO AVE.) Utility Work both directions at LM 0.31: Lane closures at the intersection of St. Elmo Avenue and w. 55th Street for utility construction. Motorists should use caution and be aware of personnel and equipment when traveling through the work zone. Signage, cones and flaggers will be present between 9:00 AM and 2:00 PM with an estimated completion of 09/02/21. [2021-474]
HAMILTON COUNTY SR-2 (BRAINERD RD.) Utility Work westbound at LM 13.84: Brainerd Road will have two westbound lanes closed for utility work between North Moore Rd and North St. Marks Avenue. Signage and barrels will be present. Motorists should expect delays and seek an alternate route between 8:00 am and 5:00 pm from 08/03/21 – 08/10/21. [2021-502]
HAMILTON COUNTY SR-2 (CUMMINGS HWY.) Utility Work eastbound at LM 2.87: Shoulder and single lane closures between Lilac Avenue and S. Moss Avenue. Signage, drums and cones will be present. Motorists should use caution and be aware of personnel and equipment between 9:00 AM and 2:00 PM from 07/08/21 through 08/18/21. [2021-362]
HAMILTON COUNTY SR-2 (E. 23RD ST.) Utility Work both directions at LM 9.16: Shoulder and single lane closures between S. Holly Street and S. Highland Park Avenue. Signage and cones will be present. Motorists should use caution and be aware of personnel and equipment between 9:00 AM and 3:00 PM through 08/11/21. [2021-111]
HAMILTON COUNTY SR-2 (E. 23RD ST.) Utility Work both directions at LM 9.82: Shoulder and single lane closures between 4th Avenue and S. Lyerly Street. Signage and cones will be present. Motorists should use caution and be aware of personnel and equipment between 9:00 AM and 2:00 PM through 08/11/21. [2021-389]
HAMILTON COUNTY SR-312 (MAHAN GAP RD.) Utility Work both directions from LM 17.12 to LM 17.26: Shoulder and single lane closures between Fire Tower Road and Owl Hollow Road. Signage, flaggers, and cones will be present. Motorists should use caution and be aware of personnel and equipment between 9:00 AM and 2:00 PM from 07/15/21 through 08/25/21. [2021-359]
HAMILTON COUNTY SR-8 (TAFT HWY.) Utility Work northbound at LM 21.35: Shoulder and single lane closures between Hollister Road and McAmis Road. Signage, flaggers and cones will be present. Motorists should use caution and be aware of personnel and equipment between 9:00 AM and 3:00 PM from 07/15/21 through 08/11/21. [2021-048]
HAMILTON COUNTY SR-29 (US-27) repair of the bridge over Big Soddy Creek (LM 20.6): The contractor will be performing bridge & roadway repair on the SR-29 bridge over Big Soddy Creek. During this report period the contractor will have temporary road closures. At least one lane of traffic in both directions shall always remain open.
[Mid-State Construction Company, Inc./Osbonlighter/CNU046]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, to install power poles and transfer lines. The flagging operations will be performed on 08/05/21, 08/06/21, 08/09/21, 08/10/21, and 08/11/21 from 7:00 AM to 1:00 PM and 3:00 PM to 7:00 PM. Closures will last about 2 hours per location. There will also be very short lane closures for blasting that will last five minutes or less. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY SR-319 (Amnicola Highway) bridge repair over SR-153:The contractor will be performing bridge repair operations on the Amnicola (SR-319) bridge over SR-153. During this project, SR-319 will have lane closures in place & SR-153 may have lane closures as well. The bridge repair over SR-153 will be performed between 8:00 PM& 6:00 AM. During repair operations at least one lane of traffic will remain open in both directions.
[Mid-State Construction Company, Inc./Osbonlighter/CNV053]
HAMILTON COUNTY SR-321 resurfacing from north of SR-317 (LM 5.58) to near US-11 (US-64, SR-2) (LM 7.08), including bridge expansion joint repair: During this report period, the contractor will have temporary lane closures while performing resurfacing operations. One lane of traffic willalways remain open. Flaggers will be present to maintain traffic flow.
[Talley Construction Company, Inc./Osbonlighter/CNV054]
HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be grading, paving, constructing retaining wall(s) and installing signals & lighting on the S.I.A. route connecting Ferdinand Piech Way & Volkswagen Dr. **The roadway is not open to traffic**.Motorists should be alert to the entrance and exit of construction vehicles from the jobsite onto the connecting roadways. Flaggers may be onsite directing traffic.
[Talley Construction Company, Inc./Osbonlighter/CNU221]