District 29
HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): During this reporting period, the contractor will be working in the area of Market Street (SR-58) and I-24 to implement a new traffic pattern. On 06/07/2021, the contractor will close the ramp to I-24 Eastbound at Long Street and the cloverleaf ramp from Market Street (SR-58) Southbound to I-24 Eastbound. Traffic in these areas accessing I-24 Eastbound will do so via a temporary signal located just south of the I-24 underpass on Market Street (SR-58). Detour signage will be in place. Brief, intermittent lane closures are possible on Market Street at the intersection with I-24 during daylight hours as the contractor works on the installation of the temporary signal.
[Wright Brothers Construction Company, Inc./Wagner/CNU011]
HAMILTON COUNTY I-24 Replacement of Belvoir Ave. bridge over I-24 and I-24 bridges over Germantown Road near MM 183: Single and double alternating lane closures on I-24 EB and WB will be used on 06/03/21, 06/06/21 through 06/09/21 from 9 PM and 6 AM. Additionally, there will be single lane closures on North and South Terraces and in the north and south directions of Germantown Road under the I-24 Bridge and at the intersections of Germantown with North and South Terrace on 06/03/21, 06/04/21, and between 06/07/21 and 06/09/21 from 9 PM and 6 AM. There is a 45 MPH speed limit reduction throughout the project corridor on I-24.
[Bell and Associates Construction, LP/Blevins/CMGC03]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: Phase 3 traffic alignments have been implemented. Watch for trucks entering and exiting project. Traffic should expect multiple lane shifts traveling through the interchange. Lane closures will occur Sunday nights through Thursday nights between 9 PM and 6 AM at the following locations: I-75 NB MM 1, I-75 SB MM 3 and I-24 EB MM 184.0 Traffic pacing may occur throughout interchange Sunday nights through Thursday nights between 9 PM and 6 AM. Additionally, there may intermittent shoulder closures at various locations for access to the median and roadside areas. The Welcome Center has been reopened. The speed limit has been reduced to 45 MPH throughout the interchange.
[C.W. Matthews Contracting Company, Inc./Blevins/DB1801]
HAMILTON COUNTY US-27 (I-124) widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: No lane closures are scheduled for the week of 06/03/21 thru 06/08/21.
[Dement Construction Company, LLC/Curtis/CNP230]
HAMILTON COUNTY SR-2 (DODDS AVE.) Utility Work both directions from LM 10.10 to LM 10.68: Lane closures will cause delays on Dodds Avenue between East 23rd Street and E 14th Street. Motorists should reduce speed and be prepared to stop or use alternate routes when possible. Signage, cones, barricades, and flaggers will be present between the hours of 7 AM and 7 PM with an estimated completion of 6/28/21. [2019-507]
HAMILTON COUNTY SR-8 (MARKET ST.) Utility Work southbound at LM 8.95: Single lane closure at the southwest corner of Market St/ E ML King Blvd intersection. Signage and barricades will be present. Motorists should use caution through the area and be aware of personnel and equipment between 10 AM and 3:30 PM with an estimated completion of 6/9/21. [2021-162]
HAMILTON COUNTY SR-29 (US-27) repair of the bridge over Big Soddy Creek (LM 20.6): The contractor will be performing bridge & roadway repair on the SR-29 bridge over Big Soddy Creek. During this report period the contractor will have one lane of SR-29 north-bound closed. At least one lane of traffic in both directions shall always remain open.
[Mid-State Construction Company, Inc./Osbonlighter/CNU046]
HAMILTON COUNTY SR-2 (US-64, US-11) improvement of the intersection at Edgmon Road in Collegedale (LM 22.7), including grading, drainage, and paving: Extra care should be taken while trucks are entering and exiting the roadway. One lane might be intermittently closed while work is ongoing. The public is advised to be aware of the newly established traffic pattern at the intersection. Additional flaggers will be onsite as needed.
[Talley Construction Company, Inc./Osbonlighter/CNU012]
HAMILTON COUNTY SR-312 resurfacing from south of Henry Road (LM 6.9) to west of SR-58 (LM 14.2): During this reporting period, there will be intermittent lane closures on this road as the Contractor will have flaggers directing traffic for the construction operation. The motoring public should expect possible long delays.
[Wright Brothers Construction Company, Inc./Curtis/CNV087]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, to install power poles and transfer lines. The flagging operations will be performed on 06/03/21, 06/04/21, 06/07/21, 06/08/21, and 06/09/21 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. There will also be a very short lane closure for blasting that will last five minutes or less on 06/09/21 off Spalding Drive and Tucker Road. The contractor will be shifting traffic on Chestnut Creek Road to the temporary alignment. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY SR-319 (Amnicola Highway) bridge repair over SR-153: Contractor will be performing bridge repair operations on the Amnicola (SR-319) bridge over SR-153. During this project, SR-319 will have lane closures in place & SR-153 may have lane closures as well. Bridge repair over SR-153 will be performed between 8pm & 6am. During repair operations at least one lane of traffic shall remain open in all directions.
[Mid-State Construction Company, Inc./Osbonlighter/CNV053]
HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be grading, paving, constructing retaining wall(s) and installing signals & lighting on S.I.A. route connecting Ferdinand Piech Way & Volkswagen Dr. **The roadway is not open to traffic**. The traveling public should be alert to the entrance and exit of construction vehicles from the jobsite onto the connecting roadways. Flaggers may be onsite directing traffic.
[Talley Construction Company, Inc./Osbonlighter/CNU221]