HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): Williams Street is closed to all traffic at the I-24 underpass to support the installation of new storm drainage structures for the new frontage road. Traffic will still be able to access the ramps to I-24 and US-27, but no through traffic will be allowed on Williams Street between West 21st Street and West 25th Street. Traffic will detour around the closure via West 21st Street and Broad Street. Signs will be posted. The contractor will be working on new bridge construction, storm drainage structures, and utility relocation. Chestnut Street is closed at the I-24 underpass and will remain closed until the construction of bridge #2 is complete. Detour routes are posted. The US-27 N on-ramp at William St. has been closed and it will be closed until the new alignment for this ramp is completed. There will be marked detour signs to use the Broad St. US-27 on-ramp. The contractor has opened up the new Broad St exit off I24 and closed the existing exit to the Broad St that is off the US27 S exit. Traffic from US27 S that needs to get to Broad St. will use the Williams St. Exit. There will be detour signs to direct traffic off the Williams St. exit to Broad St. Also, with the new exit there will be a new signal at the intersection of the new exit and Broad St. Drivers need to be aware of these changes. The US 27 S ramp onto I24 East will be reduced to 2 lanes with the Williams St. exit remaining open. The ramp will be this way for several months and drivers are advised to use caution in this area.
[Wright Brothers Construction Company, Inc./Curtis/CNU011]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction Phase 2: Weather permitting, the contractor will implement single lane closures between the hours of 9 PM until 6 AM Sunday through Thursday, at following locations: I-24 WB MM 185 to MM 183, I-24 EB MM 183 to MM 185, and North Terrace.
[Wright Brothers Construction Company, Inc./Maj Prj – Blevins/DB2101]
HAMILTON COUNTY I-75 concrete repair from MM 6.6 to MM 12.8: During this reporting period, the contractor will be having lane closures in both directions on I-75 from 9 PM-6 AM on Thursday, and Sunday thru Wednesday. During these lane closures, the contractor might have to temporary close some of the ramps so that they can work on the ramp.
[Summers-Taylor, Inc./Curtis/CNW046]
HAMILTON COUNTY SR-17 resurfacing from the Georgia state line (LM 0) to SR-2 (US-11, US-64, US-72, LM 2.2): During this reporting period, there will be lane closures during the day as the contractor will be starting to mill the roadway. There will be flaggers stopping traffic as this work is being done. Drivers need to expect possible long delays as this work is going on.
[Talley Construction Company, Inc./Curtis/CNW213]
HAMILTON COUNTY SR-2 (CUMMINGS HWY.) Utility Work eastbound from LM 2.25 to LM 2.8: Shoulder and single lane closures between Birmingham Hwy and Lilac Avenue. Motorists should reduce speed and be prepared to stop. Trucks, signage, and cones/barrels will be present, 01/03/23 through 01/24/23 from 9 am – 2 pm. [2022-624]
HAMILTON COUNTY SR-2 (US-11, US-64) McCallie Tunnel cleaning: The contractor will be cleaning this tunnel on Wednesday from 8 PM-6 AM. As this work is being done, there will be one lane closed in each direction.
[Diamond Specialized, Inc./Curtis/CNW197]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for utility work. The flagging operations will be performed on 01/12/23, 01/13/23, 01/16/23, 01/17/23 and 01/18/23 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment. Nighttime flagging operations will also be required on Spalding Drive on 01/16/23 and 01/17/23 for setting of Bridge #1 beams.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY SR-8 (E. MAIN ST.) Utility Work eastbound from LM 5.94 to LM 6.38: Shoulder and single lane closures from S. Orchard Knob Ave and S. Watkins Street. Motorists should reduce speed and be prepared to stop. Trucks, signage, and barrels will be present, 12/01/22 through 01/31/23 from 9 am – 2 pm. [2022-754]
HAMILTON COUNTY SR-8 (TAFT HWY.) Utility Work northbound from LM 20.09 to LM 22.96: Shoulder and single lane closures from Anderson Pike and Edgewood Drive. Motorists should reduce speed and be prepared to stop. Trucks, signage, flaggers, and cones/barrels will be present, 01/05/23 through 01/20/23 from 9 am – 2 pm. [2022-799]
HAMILTON COUNTY SR-8 (US-127) construction near Palisades Road (LM 15.2) to near Sunset Drive (LM 15.4): The contractor has closed the right lane going up the Signal Mountain Road from LM 15 (about 1/2 Mi from Palisades Road) to past Sunset Drive. This closure will be in effect for several months during the duration of this project. There will be intermittent lane closures on Signal Mountain Road as the contractor will have flaggers out as they work. Due to the possibility of flaggers stopping traffic, traffic should be aware of possible delays in this area.
[Wright Brothers Construction Company, Inc./Curtis/CNW001]
HAMILTON COUNTY SR-8 (US-127) Stringers Ridge Tunnel cleaning: On Wednesday of this reporting period from 8 PM-6 AM, the tunnel will be closed as the contractor washes the tunnel. There will be signs directing traffic to go for the detour around the closure.
[Diamond Specialized, Inc./Curtis/CNW197]