HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): Williams Street is closed to all traffic at the I-24 underpass to support the installation of new storm drainage structures for the new frontage road. Traffic will still be able to access the ramps to I-24 and US-27, but no through traffic will be allowed on Williams Street between West 21st Street and West 25th Street. Traffic will detour around the closure via West 21st Street and Broad Street. Signs will be posted. The contractor will be working on new bridge construction, storm drainage structures, and utility relocation. Chestnut Street is closed at the I-24 underpass and will remain closed until the construction of bridge #2 is complete. Detour routes are posted. The US-27 N on-ramp at Williams St. has been closed and it will be closed until the new alignment for this ramp is completed. There will be marked detour signs to use the Broad St. US-27 on-ramp. The contractor has opened up the new Broad St. Exit off I24 and closed the existing exit to the Broad St off the US27 S exit. Traffic from US27 S that needs to access Broad St. will use the Williams St. exit. There will be detour signs to direct traffic off the Williams St. exit to Broad St. Also, with the new exit there will be a new traffic signal at the intersection of the new exit and Broad St. On Thursday night from 9 PM-6 AM, the contractor will be closing one lane on the US27 S exit to I24 E to work on the overhead signs. On Friday night starting at 9 PM until Saturday morning at 10 AM, the contractor will also close one lane on the US27 S ramp to I24 E so they can pour the overhead footers for the project. On Friday of this reporting period, the contractor will have intermittent lane closures on East 20th Street near Broad St so that they can remove the temporary bike lanes and restripe in this area.
[Wright Brothers Construction Company, Inc./Curtis/CNU011]
HAMILTON COUNTY I-75 concrete repair from MM 6.6 to MM 12.8: During this reporting period, the contractor will be having lane closures in both directions on I-75 from 9 PM-6 AM. During these lane closures, the contractor might have to temporary close some of the ramps so that they can work on the ramp.
[Summers-Taylor, Inc./Curtis/CNW046]
HAMILTON COUNTY SR-153 resurfacing from LM 3.5 to LM 3.7, including bridge expansion joint repair on the railroad overpass bridge (LM 3.6); SR-2 resurfacing on (US-11, US-64) from the NB interstate ramps (LM 20.6) to the Bradley County line (LM 24.4): During this reporting period, the contractor will have intermittent lane closures on SR-153, LM 3.6 to perform a resurfacing operation starting on 10/24/2022, between 7 PM and 6 AM. The traveling public is encouraged to be aware of safety personnel and construction vehicles entering and exiting the jobsite.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNW131]
HAMILTON COUNTY SR-17 resurfacing from the Georgia state line (LM 0) to SR-2 (US-11, US-64, US-72, LM 2.2): Starting during this reporting period, the contractor will have intermittent lane closures as they begin on this project.
[Talley Construction Company, Inc./Curtis/CNW213]
HAMILTON COUNTY SR-2 (CUMMINGS HWY.) TDOT Maintenance both directions from LM 3.3 to LM 5.75: During this reporting period, TDOT maintenance crews will have lane closures on Cummings Highway between LM 3.3 and LM 5.75 for vegetation removal. Traffic will be reduced to one lane in each direction during this operation. Motorists are advised to reduce speed in the work zone and watch for trucks entering/leaving the highway.
HAMILTON COUNTY SR-29 (US-27) slide repair between LM 29 and LM 30: During this reporting period, TDOT Maintenance and contract forces will have traffic reduced to one lane in each direction on US-27 (SR-29) to continue work on a new retaining wall and slope stabilization. Motorists are advised to reduce speed in the work zone.
[GeoStabilization International, LLC /Maint – Chattanooga/MAINT]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, for utility work. The flagging operations will be performed on 10/20/22, 10/21/22, 10/24/22, 10/25/22, and 10/26/22 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment. Traffic has been shifted onto the new alignment of SR-317 by the existing intersection of Apison Pike and University Drive and by Eastview Terrace. The tie-in of College Drive to SR-317 has been closed and a detour route is in place.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY SR-317 (BONNY OAKS DR.) Utility Work westbound from LM 4.55 to LM 4.54: Shoulder and single lane closures from Lee Hwy and Silverdale Road. Motorists should reduce speed and be prepared to stop. Trucks, signage, drums, and flaggers will be present, 09/22/22 through 10/26/22 from 9 am – 2 pm. [2022-475]
HAMILTON COUNTY SR-8 (US-127) construction near Palisades Road (LM 15.2) to near Sunset Drive (LM 15.4): The contractor has closed the right lane going up the Signal Mountain Road from LM 15 (about 1/2 mile from Palisades Road) to past Sunset Drive. This closure will be in effect for several months during this project. Also, there will several intermittent lane closures daily on SR8 (Signal Mountain Road) as the contractor is works to remove brush on this project for the next couple of weeks.
[Wright Brothers Construction Company, Inc./Curtis/CNW001]
HAMILTON COUNTY SR-8 (US-41, US-76) Bachman Tubes cleaning: On Thursday night of this reporting period, the contractor will close the tunnels from 8 PM-6 AM to clean it. There will be a signed detour for traffic to follow to get around the closure.
[Diamond Specialized, Inc./Curtis/CNW197]
HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be performing resurfacing operations starting 10/20/2022 throughout the intersection connecting the S.I.A. route, Ferdinand Piech Way, & Volkswagen Dr. The new 4-way signalized intersection will continue to operatorial & traffic has been shifted to the new alignment. Traveling public should be cautious of the new traffic pattern and lane shifts in effect including a lowered speed limit. The traveling public should also be alert to the entrance and exit of construction vehicles & staff on and around the jobsite and the connecting roadways. Flaggers may be onsite directing traffic.
[Talley Construction Company, Inc./Osbonlighter/CNU221]