Beginning on Friday, July 14, crews will begin the following schedule for the I-24/I-75 Interchange Phase II Project along with the McBrien Road and Moore Road bridge closure and replacement project.
Ramp closures on July 14 will happen Friday night after 9 pm. The bridge and ramp closures scheduled for July 19 will be throughout the day. The work will start shortly after morning rush hour around 9 am. All work is weather permitting, and if it can’t take place will be rescheduled for the next dry day.
Friday, July 14, 2023
Close Exit 184 – I-24 EB Moore Road
Close Exit 183A – I-24 WB Belvoir Ave
Wednesday, July 19, 2023
Close Entrance Ramp I-24 WB – North Terrace between Moore Rd and Belvoir
Close Entrance Ramp I-24 EB – South Terrace Between Belvoir and Moore Rd
Close Moore Road Bridge
Close McBrien Road Bridge
Open Continuous Detour U-Turn between Belvoir and Spring Creek
During this closure, all traffic attempting to access McBrien Road or Moore Road bridges will be redirected to alternate routes where detour signs will be placed to re-direct traffic. In the event of an emergency, please contact East Ridge Police Department at 423-622-1725 or dial 911.