HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): During this reporting period the contractor will be working on new bridge construction, retaining wall construction, and the placement of new overhead signs. Beginning Monday 11/01/21 through Thursday 11/04/21 at 9 PM to 6 AM daily the contractor will close the left (#1) lane of I-24 Westbound to support the construction of foundations for new overhead signs. Chestnut street is closed at the I-24 underpass and will remain closed until the construction of bridge #2 is complete. Detour routes are posted.
[Wright Brothers Construction Company, Inc./Wagner/CNU011]
HAMILTON COUNTY I-24 Replacement of Belvoir Ave. bridge over I-24 and I-24 bridges over Germantown Road near MM 183: The contractor is working on final striping throughout project. Single and double alternating lane closures on I-24 EB and WB are planned from 9 PM and 6 AM Sunday nights through Thursday nights to accommodate striping activities. There is a 45 MPH speed limit reduction throughout the project corridor on I-24.
[Bell and Associates Construction, LP/Blevins/CMGC03]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: All roadways and ramps are in their final alignments. The contractor is now working on final items and traffic should still use caution traveling throughout the interchange. The final work items will mostly consist of off shoulder work/median work. Additionally, lane closures may still occur Sunday nights through Thursday nights between 9 PM and 6 AM to finish in roadway items. The speed limit will remain reduced to 45 MPH throughout the interchange until construction crews demobilize.
[C.W. Matthews Contracting Company, Inc./Blevins/DB1801]
HAMILTON COUNTY SR-153 (STATE HWY. 153) Utility Work both directions from LM 7.7 to LM 8.9: Nighttime shoulder and lane closure between Chickamauga Dam and Hixson Pike Overpass. Motorists should reduce speed and be prepared to stop. Caution vehicles, signage, drums, and flaggers will be present 10/04/21 through 11/10/21 between 10 pm and 6 am. [2021-558]
HAMILTON COUNTY SR-319 (HIXSON PK.) Utility Work both directions at LM 12.01: Shoulder and multi-lane closures both North and South bound directions between McConnell School Road and Dallas Hollow Road. Motorists should reduce speed and be prepared to stop. Signage, cones, and flaggers will be present, 10/28/21 through 11/12/21 from 9:00 am – 2:00 pm. [2021-590]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, to install power poles and transfer lines. Flagging operations will also be required on Tucker Road for dump trucks hauling fill dirt. The flagging operations will be performed on 10/27/21, 10/28/21, 10/29/21, 11/02/21, and 11/03/21 from 7:00 AM to 1:00 PM and 3:00 PM to 7:00 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment. The contractor is planning to flag traffic on a single lane of Tallant Road to finish the final portion of the roundabout in the upcoming weeks.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY SR-319 (Amnicola Highway) bridge repair over SR-153: The contractor will be performing bridge repair operations on the Amnicola (SR-319) bridge over SR-153. During this project, SR-319 will have lane closures in place & SR-153 may have lane closures as well. During repair operations at least one lane of traffic shall remain open in all directions.
[Mid-State Construction Company, Inc./Osbonlighter/CNV053]
HAMILTON COUNTY SR-58 resurfacing from north of Sims Road (LM 17.4) to south of SR-60 (LM 26): During the report period, one lane will be temporarily closed. There will be one lane open for traffic. Flaggers will be on site.
[Asphalt Paving Systems, Inc./Osbonlighter/CNV156]
HAMILTON COUNTY SR-8 (US-41 / US-76) resurfacing from east of East 29th St to SR-2 (US-11 / US-64) and on SR-2 (US-11 / US-64) from SR-8 (US-41 / US-76) to near the Missionary Ridge Tunnel: During this reporting period, there will be intermittent lane closures on Dobbs Avenue as the contractor works. Also, there will be intermittent lane closures on Westside Drive as the contractor works in these areas. The contractor will be closing portions of the sidewalk as they are working to install curb ramps. There will be signed sidewalk detours as this work is being performed.
[Talley Construction Company, Inc./Curtis/CNV155]
HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be grading and installing signals & lighting on S.I.A. route connecting Ferdinand Piech Way & Volkswagen Dr. **The roadway is not open to traffic**. The traveling public should be alert to the entrance and exit of construction vehicles from the jobsite onto the connecting roadways. Flaggers may be onsite directing traffic. Traveling public should be cautious of new traffic pattern in effect.
[Talley Construction Company, Inc./Osbonlighter/CNU221]