HAMILTON COUNTY I-24 interchange improvement at SR-2 (US-11, US-41, US-72, Broad Street) and SR-58 (Market Street): During this reporting period, the contractor will be working on the placement of earth fill and the construction of bridges. Beginning Monday 10/18/21 through Friday 10/22/21 at 9 PM until 6 AM the contractor will close the left (#1) lane of I-24 eastbound for the installation of new overhead sign structures. Chestnut street is closed to through traffic between West 20th Street and West 25th Street and will remain closed until the construction of bridge #2 is complete. The contractor may have brief intermittent lane closures on Broad Street (SR-2) and Market Street (SR-58) to support utility relocation Monday through Friday 8 AM to 5:30 PM.
[Wright Brothers Construction Company, Inc./Wagner/CNU011]
HAMILTON COUNTY I-24 Replacement of Belvoir Ave. bridge over I-24 and I-24 bridges over Germantown Road near MM 183: The contractor is working on final striping throughout project. Single and double alternating lane closures on I-24 EB and WB are planned from 9 PM and 6 AM Sunday nights through Thursday nights to accommodate striping activities. There is a 45 MPH speed limit reduction throughout the project corridor on I-24.
[Bell and Associates Construction, LP/Blevins/CMGC03]
HAMILTON COUNTY I-75 at I-24 Interchange Reconstruction: All roadways and ramps are in their final alignments. The contractor is now working on final items and traffic should still use caution traveling throughout the interchange. The final work items will mostly consist of off shoulder work/median work. Additionally, lane closures may still occur Sunday nights through Thursday nights between 9 PM and 6 AM to finish in roadway items. The speed limit will remain reduced to 45 MPH throughout the interchange until construction crews demobilize.
[C.W. Matthews Contracting Company, Inc./Blevins/DB1801]
HAMILTON COUNTY US-27 (I-124) widening from I-24/US-27 interchange to north of the Olgiati Bridge over the Tennessee River, including widening the Olgiati Bridge: Thursday 10/14/21 to Friday 10/15/21 7 AM- 7 PM Weather Permitting, the contractor will implement a Temporary right lane closure on WB MLK in order to close the Northbound US-27 on Ramp from WB MLK. A CMU will be placed on the ramp to warn of the upcoming closure. Traffic will be detoured using the attached detour map.
[Dement Construction Company, LLC/Curtis/CNP230]
HAMILTON COUNTY I-24 TDOT Bridge Maintenance eastbound from MM 178 to MM 179: TDOT Bridge Maintenance will be patching potholes on the deck of the I-24 Bridge, EBL, over the CSX RR, Monday, October 18th, starting at 9:00 PM. One lane will be closed with traffic control in place.
HAMILTON COUNTY I-24 TDOT Bridge Maintenance eastbound from MM 181 to MM 182: TDOT Bridge Maintenance will be patching potholes on the deck of the I-24 Bridge, EBL, over the Westside Drive (SR-8), Tuesday, October 19th, starting at 9:00 PM. One lane will be closed with traffic control in place.
HAMILTON COUNTY I-24 TDOT Bridge Maintenance westbound from MM 178 to MM 179: TDOT Bridge Maintenance will be patching potholes on the deck of the I-24 Bridge, WBL, over the ramp to US-27, Thursday, October 14th, starting at 9:00 PM. One lane will be closed with traffic control in place.
HAMILTON COUNTY I-75 TDOT Bridge Maintenance northbound at MM 3.43: TDOT Bridge Maintenance will be patching potholes on the deck of the I-75 Bridge, NBL, over East Brainard RD (SR-320), Wednesday, October 20th, starting at 9:00 PM. One lane will be closed with traffic control in place.
HAMILTON COUNTY SR-153 (STATE HWY. 153) Utility Work both directions from LM 7.7 to LM 8.9: Police assisted nighttime shoulder and multi-lane closures between Chickamauga Dam and Hixson Pike Overpass. Motorists should reduce speed and be prepared to stop. Police officers, caution vehicles, signage, drums, and flaggers will be present 10/04/21 through 10/22/21 between 10 pm and 6 am. [2021-374 / 558]
HAMILTON COUNTY SR-317 (Apison Pike) improvement project from SR-321 (Ooltewah-Ringgold Road) to east of Layton Lane: Lane closures and flagging operations will be required on SR-317, Apison Pike, to install power poles and transfer lines. Flagging operations will also be required on Tucker Road for dump trucks hauling fill dirt. The flagging operations will be performed on 10/14/21, 10/15/21, 10/18/21, 10/19/21, and 10/20/21 from 7 AM to 1 PM and 3 PM to 7 PM. Closures will last about 2 hours per location. The contractor will have intermittent flagging operations during daytime non-peak hours for utility work, delivery of materials and equipment.
[Wright Brothers Construction Company, Inc./Osbonlighter/CNT336]
HAMILTON COUNTY SR-319 (Amnicola Highway) bridge repair over SR-153: The contractor will be performing bridge repair operations on the Amnicola (SR-319) bridge over SR153. During this project, SR319 will have lane closures in place & SR153 may have lane closures as well. Bridge repair over SR153 will be performed between 8pm & 6am. During repair operations at least one lane of traffic shall remain open in all directions. **From 10.17.21 to 10.22.21, there will be lane closures on SR153 north and southbound. **
[Mid-State Construction Company, Inc./Osbonlighter/CNV053]
HAMILTON COUNTY SR-58 resurfacing from north of Sims Road (LM 17.4) to south of SR-60 (LM 26): During the report period, one lane will be temporarily closed. There will be one lane open for traffic. Flaggers will be on site.
[Asphalt Paving Systems, Inc./Osbonlighter/CNV156]
HAMILTON COUNTY SR-8 (US-41 / US-76) resurfacing from east of East 29th St to SR-2 (US-11 / US-64) and on SR-2 (US-11 / US-64) from SR-8 (US-41 / US-76) to near the Missionary Ridge Tunnel: During this reporting period, there will be intermittent lane closures on Dobbs Avenue as the contractor works. The contractor will be closing portions of the sidewalk as they are working to install curb ramps. There will be signed sidewalk detours as this work is being performed.
[Talley Construction Company, Inc./Curtis/CNV155]
HAMILTON COUNTY SR-8 (US-41, US-76) Bachman Tubes cleaning: On Thursday night of this reporting period, the contractor will be temporarily closing the tunnels from 8 PM-6 AM to clean them. There will be a signed detour for traffic to follow to get around the closure.
[Diamond Specialized, Inc./Curtis/CNV157]
HAMILTON COUNTY The construction of an S.I.A. to VW: The contractor will be grading and installing signals & lighting on S.I.A. route connecting Ferdinand Piech Way & Volkswagen Dr. **The roadway is not open to traffic**. The traveling public should be alert to the entrance and exit of construction vehicles from the jobsite onto the connecting roadways. Flaggers may be onsite directing traffic. The traveling public should be cautious of new traffic pattern in effect.
[Talley Construction Company, Inc./Osbonlighter/CNU221